Updates: last update's detail


Offers and Services / Connection / Generation / Accommodation capacities.

Source: RTE 01/07/2004

RTE is publishing the accommodation capacities of substations on the transmission grid.

Taking the opportunity of the publication of a new "Procedure for processing generating installations' connection requests", RTE is publishing the accommodation capacities of substations on the transmission grid. These data will soon be available on the distribution system operator's website: http://www.grd.edf.fr. They will be added to gradually as this complementary data procedure comes into force, along with the volume of projects on waiting lists, the volume of requests that have not gone onto waiting lists over the last six months and the residual transformation accommodation capacity of HVA and HVB substations.

Consult our new section : "Offers and services / Connection / Generation / Accommodation capacity".