Updates: last update's detail


France - Italy Interconnection

Source: RTE 21/02/2001

Results of the process for the allocation of interconnection capacity between France and Italy.

The process for the allocation by RTE of interconnection capacity between France and Italy got under way on 16 February 2001 with the opening of the envelopes sent by the requesting parties. A total of 57 envelopes were received, including 2 that were not within the deadlines and which therefore remained unopened. Out of the remaining 55 requests, 4 were considered as inadmissible because they did not comply with the presentation instructions laid down.
The results of the allocation of the 2,400 MW are as follows:

* As concerns the capacity awarded under contracts entered into prior to the coming into force of Directive 96/92/EC, the requests were below the capacity proposed, and 1,855 MW were therefore awarded without applying a proportional share;

* As concerns the rest of the capacity, the remaining 545 MW were awarded by applying the mechanism described in the published documents. The final ratio coefficient between the power granted and the power requested is equal to 8.1%.

In conclusion, the proposed capacity is awarded to the 46 requesting parties listed below in alphabetical order:

- ACCIAIERIA ISP DI CREMONA SRL
- ACCIAIERIE DI CALVISANO SPA
- AICE SCARL
- ALFA ACCIAI SCPA
- ASM ENERGIA E AMBIENTE SRL
- ASSOENERGIA ScpA
- BKW FMB ENERGIE SA
- BP ITALIA
- CENTOMILACANDELE SCPA
- COMILOG ITALIA
- CONSORZIO BRESCIA ENERGIA
- CONSORZIO DEL TORRENTE PESCIA SPA
- DUFERDOFIN SPA
- DUKE ENERGY INTERNATIONAL TRADING AND MARKETING
- DYNEGY MARKETING AND TRADING
- E.NOI Spa
- E.ON Trading GmBH
- EDF
- EDISON ENERGIA SPA
- ELECTRABEL SA
- ELECTRICITE DE LAUFENBOURG SA
- EnBW
- ENDESA ENERGIA S.A.
- ENECO TRADE SRL
- ENICHEM SPA
- ENIPOWER TRADING SPA
- EOS
- FERALPI SIDERURGICA SPA
- FERRERO SPA
- FERRIERE NORD SPA
- FIAT AUTO SPA
- INNOGY PLC
- ITALCEMENTI SPA
- LUMENERGIA SCRL
- RADICI ENERGIE SRL
- RIVA ACCIAIO SPA
- RWE TRADING GmbH
- SADEPAN CHIMICA SRL
- SAINT GOBAIN VETRI SPA
- SATA SPA
- TELECOM ITALIA SPA
- TRAFIGURA Electricity BV
- TRAFILERIE CARLO GNUTTI SPA
- TXU-EET BV
- VERBUND
- VIDEOCOLOR SPA

Only requesting parties for whom the result of this calculation leads to a value greater than or equal to 1 MW are shown on this list.
The beneficiaries will receive confirmation in writing and details concerning the capacity awarded to them, as well as the capacity awarded in summer for the period from 16 to 31 August. The non-linked capacity awarded to each beneficiary can be calculated by multiplying his non-linked request by the final ratio, rounded off to the nearest value.

Contact: Michel Derdevet
01.41.02.19.73

Please go to our Web site for further information on the allocation of transmission capacities between France and Italy.