Unavailibility of the transmission network / NTC Impact

  • Data is now available on Data portal

RTE provides the planned and unplanned unavailability of elements on its network, having an impact on cross border capacities.

The planned unavailabilities are published once they have been validated by operational teams, who are in charge of the maintenance of the planned works dates.

An outage is:

  • Ongoing, if its start date has passed but its end date is in the future
  • Planned if its start date is in the future
  • Closed if its start and end dates have passed
  • Cancelled if RTE considers that the outage is no longer valid.

17 unavailability(ies), per page
Page 1 / 1
List of closed unavailabilities (total and partial)
Outage type Start Real end Unavailable Asset Border(s) impacted Cause Details
Planned maintenance
15/09/2020 08:00 15/09/2020 17:00 L 225kV N0 1 MARSILLON-PRAGNERES Spain Foreseen Maintenance / Maintenance prévue Details
Planned maintenance
14/09/2020 09:00 14/09/2020 11:00 Mandarins-Sellindge 2 England Foreseen Maintenance / Maintenance prévue Details
Planned maintenance
14/09/2020 07:30 18/09/2020 17:00 L 400kV N0 2 BEZAUMONT-VIGY Germany, Belgium Foreseen Maintenance / Maintenance prévue Details
Planned maintenance
11/09/2020 14:50 14/09/2020 07:00 Achène-Lonny Germany, Belgium Foreseen Maintenance / Maintenance prévue Details
Planned maintenance
10/09/2020 07:30 11/09/2020 17:00 L 400kV N0 2 CHEVALET-WARANDE Germany, Belgium Foreseen Maintenance / Maintenance prévue Details
Planned maintenance
09/09/2020 00:00 09/09/2020 17:00 Achène-Lonny Germany, Belgium Foreseen Maintenance / Maintenance prévue Details
Planned maintenance
09/09/2020 00:00 09/09/2020 23:00 Mandarins-Sellindge 2 England Foreseen Maintenance / Maintenance prévue Details
Forced unavailability
07/09/2020 12:45 08/09/2020 23:59 Mandarins-Sellindge 1 England Failure / Défaillance Details
Forced unavailability
07/09/2020 09:02 07/09/2020 12:45 Mandarins-Sellindge 1 England Failure / Défaillance Details
Planned maintenance
07/09/2020 09:00 07/09/2020 17:00 L 225kV N0 1 MARSILLON-PRAGNERES Spain Foreseen Maintenance / Maintenance prévue Details
Planned maintenance
07/09/2020 07:30 17/09/2020 19:00 Biescas-Pragnères Spain Foreseen Maintenance / Maintenance prévue Details
Planned maintenance
07/09/2020 07:30 11/09/2020 17:00 Laufenburg-Sierentz (Wiesental Nord) Switzerland Foreseen Maintenance / Maintenance prévue Details
Planned maintenance
07/09/2020 07:30 11/09/2020 17:00 L 400kV N0 1 BEZAUMONT-VIGY Germany, Belgium Foreseen Maintenance / Maintenance prévue Details
Planned maintenance
01/09/2020 07:00 09/09/2020 23:00 Mandarins-Sellindge 2 England Foreseen Maintenance / Maintenance prévue Details
Planned maintenance
31/08/2020 08:00 06/09/2020 19:00 Vic-Baixas Spain Foreseen Maintenance / Maintenance prévue Details
Planned maintenance
31/08/2020 07:30 09/09/2020 17:00 L 400kV N0 1 AVELIN-WEPPES Germany, Belgium Foreseen Maintenance / Maintenance prévue Details
Planned maintenance
05/08/2020 07:30 08/09/2020 17:00 Aubange-Mont Saint Martin Germany, Belgium Foreseen Maintenance / Maintenance prévue Details
Archives
Years Files
2022 File.zip zip
2021 File.zip zip
2020 File.zip zip
2019 File.zip zip
2018 File.zip zip
2017 File.zip zip
2016 File.zip zip
2015 File.zip zip
2014 File.zip zip