Generation forecast for the next day






For the selected day, the curve above shows the generation forecast (prepared in D-1) for generating units belonging to the perimeter of UFE’s Programming Responsible Entities. Information supplied by Programming Responsible Entities is hosted and published by RTE every day between 18:00 and 20:00 for the next day. The data given for each hourly interval distinguishes between programmable and non-programmable units. These data concern generation that programming managers plan to inject into the network. They do not take into account changes that may occur on the day D.

Programmable generation units include Generation Entities (‘EDP’) for which the programming manager provides a running programme daily, for the next day.

Non-programmable generation units include forecast Generation Entities (‘EDPrev’) for which generation the following day needs to be estimated, due to its intermittency. They notably include solar, wind, run-of river hydro-electric and incineration plants (waste, industrial process gases).


Hours Generation forecast for programmable generation Generation forecast for non-programmable generation Hours Generation forecast for programmable generation Generation forecast for non-programmable generation
00:00 - 00:30 51326 4642 00:30 - 01:00 48978 4596
01:00 - 01:30 47672 4387 01:30 - 02:00 47324 4251
02:00 - 02:30 47586 4158 02:30 - 03:00 46415 4112
03:00 - 03:30 45299 4056 03:30 - 04:00 44315 3997
04:00 - 04:30 44425 3937 04:30 - 05:00 44050 3881
05:00 - 05:30 44365 3822 05:30 - 06:00 44553 3785
06:00 - 06:30 44715 3773 06:30 - 07:00 45439 3743
07:00 - 07:30 47486 3773 07:30 - 08:00 48437 3835
08:00 - 08:30 48597 3957 08:30 - 09:00 49567 4102
09:00 - 09:30 50438 4564 09:30 - 10:00 50888 4802
10:00 - 10:30 50860 5311 10:30 - 11:00 50847 5530
11:00 - 11:30 50671 5760 11:30 - 12:00 50839 5965
12:00 - 12:30 51226 6053 12:30 - 13:00 51387 6128
13:00 - 13:30 50465 5858 13:30 - 14:00 48935 5837
14:00 - 14:30 48176 5742 14:30 - 15:00 47727 5590
15:00 - 15:30 47554 5346 15:30 - 16:00 47399 5112
16:00 - 16:30 47801 4846 16:30 - 17:00 47714 4536
17:00 - 17:30 48018 4373 17:30 - 18:00 48695 4200
18:00 - 18:30 51002 4383 18:30 - 19:00 52837 4354
19:00 - 19:30 53433 4335 19:30 - 20:00 52784 4326
20:00 - 20:30 52181 4263 20:30 - 21:00 51140 4279
21:00 - 21:30 49890 4245 21:30 - 22:00 49349 4273
22:00 - 22:30 48909 4241 22:30 - 23:00 50788 4268
23:00 - 23:30 51125 4018 23:30 - 24:00 51188 4046
Download data
Download data in Excel format
Year Download
2014 File.zip zip
2013 File.zip zip
2012 File.zip zip
2011 File.zip zip

Legal disclaimer

By accessing this website, each user accepts the present disclaimer.

All production data published on this website are for energy-market players only. Such players undertake to take appropriate steps to verify the quality of the published data. As a consequence, each user acknowledges that he/she uses such published data and information at its own risks.

The freely published production data are for information purposes only and are not legally binding. The producers participating to these publications and RTE make their best efforts to provide the information they have at their disposal on the publication dates, except in case of force majeure. In particular, the provisional information constitute the producers’ best estimate at the time of the publication and are not legally binding ; they may vary, notably on the basis of analysis that may be carried out on technical and surety aspects. The producers give no warranty whatsoever as to the updating of the estimates due to new information.

RTE and the electricity producers disclaim all liability in case of total or partial interruption of the publications and disclaim all liability for loss or damage which may result from the use by third parties of the data and/or information so published, including any mistakes, inaccuracies, or omissions in the data and/or information to the fullest extent permitted by law.

RTE and the producers shall not be liable for any damage resulting from the use of the data and/or information, except in case of wilful misconduct (« faute intentionnelle avérée ») and provided the user demonstrates a direct link between the wilful misconduct and the damage or the loss he/she suffers.