Annual forecast NTC during the planned maintenance

Annual forecast NTC during the planned maintenance Archives

Interconnection between France and Italy


Forecast data
Year of works Date of update
2013 17/05/2013
Net Transfer Capacity (NTC in MW)
Date of start of works Date of end of works Export Import Type
01/07/2013 11/07/2013 1160 * P
12/07/2013 26/07/2013 1060 * P
19/08/2013 07/09/2013 1160 * P
Download the data

P = Planned works    DR = Damage repairs