Forecast and effective availability

With the implementation of market coupling on CWE, the PXs Gate Closure Time (GCT) has been postponed from 11 am (CET)  to 12 am (CET).
RTE and the french power generators (through the Union Française de l’Electricité) have taken a certain number of commitments that will be fulfilled : most of the data related to Power generation in France will be released at 11am (CET) , namely one hour before GCT

Effective availability at the daily peak time


Click the key to hide / display the desired curve.


Forecast table (in MW) - Last update 19/05/2013
Day Nuclear Coal Gas Fuel-oil + Peak Lake hydropower Hydropower
Sunday
 12/05/2013
42436 4205 3462 4162 11750 9425
Monday
 13/05/2013
46586 3620 3926 3244 11072 9216
Tuesday
 14/05/2013
46452 3620 3916 3244 10616 9163
Wednesday
 15/05/2013
45863 4205 3897 3064 9925 9246
Thursday
 16/05/2013
46400 4205 3909 3047 8744 9230
Friday
 17/05/2013
44638 3955 4354 3034 10733 9259
Saturday
 18/05/2013
43809 NR NR 3496 11307 9398
Download the data

NR : not received. Data from at least one generator have not been received by RTE.
The following rule is implemented when on day D, RTE does not receive data from generator G for one generation technology.

Origin of data

Effective availability data are compiled by generators and aggregated by RTE for each type of generation technology, prior to publication.

Effective availability data for day D published on day D+1 is made of the forcast availability evaluated on D-1, corrected with total unplanned outages recorded on day D.

The published data represent the effective net available power : the power consumed for the functioning needs of generating units (consumption of auxiliary transformer) is not estimated.

To learn more about the specifications of publication on this website, click on this link


Archives
Years Files
2013 Fichier.zip zip
2012 Fichier.zip zip
2011 Fichier.zip zip
2010 Fichier.zip zip
2009 Fichier.zip zip

Legal disclaimer

By accessing this website, each user accepts the present disclaimer.

All production data published on this website are for energy-market players only. Such players undertake to take appropriate steps to verify the quality of the published data. As a consequence, each user acknowledges that he/she uses such published data and information at its own risks.

The freely published production data are for information purposes only and are not legally binding. The producers participating to these publications and RTE make their best efforts to provide the information they have at their disposal on the publication dates, except in case of force majeure. In particular, the provisional information constitute the producers’ best estimate at the time of the publication and are not legally binding ; they may vary, notably on the basis of analysis that may be carried out on technical and surety aspects. The producers give no warranty whatsoever as to the updating of the estimates due to new information.

RTE and the electricity producers disclaim all liability in case of total or partial interruption of the publications and disclaim all liability for loss or damage which may result from the use by third parties of the data and/or information so published, including any mistakes, inaccuracies, or omissions in the data and/or information to the fullest extent permitted by law.

RTE and the producers shall not be liable for any damage resulting from the use of the data and/or information, except in case of wilful misconduct (« faute intentionnelle avérée ») and provided the user demonstrates a direct link between the wilful misconduct and the damage or the loss he/she suffers.