Unplanned outages of generating units (partial and total)
Within a delay of 30 minutes after an total or partial unplanned unavailability of a generating unit over 100 MW occurs, the responsible generator sends information to RTE which displays it on this webpage.
A unit is declared unavailable in case of:
- Unplanned outage of a unit over 100 MW
A unit is declared partially unavailable in case of:
- Unplanned reduction of more than 100 MW of available power of the unit
The information displayed contains the name, the technology and the installed capacity of the generating unit, the date and time of the outage start and if applicable the available capacity.
Information can be completed with the reason of the unavailability and its estimated end date until the morning of the day following the outage.
After this deadline, the case is closed (under the « Closed » tab) and the availability of the generating unit should be followed up through the publication of detailed availability forecasts of generating units.
Should the generator have sent an incorrect information, the data can, on its request, be moved under the « Cancelled » tab.
| Generation type | Lake hydropower |
| Name of the generating unit | REVIN 4 |
| Installed capacity of the generating unit | 202 MW |
| Available capacity | 0 MW |
| Unavailability start | 07/03/2012 18:42 |
| Reason | Control and instrumentation |
| Estimated stop date of the unavailability | 07/03/2012 19:43 |
|
Notice: This message has been displayed within 30 minutes after the outage incidence and has been completed no later than the morning of the following day. |
|
| Date and time of the last update | 08/03/2012 08:53 |
| Date and time of the first message regarding the outage |
Date and time of the last update |
Name of the generating unit concerned | Installed capacity of the generating unit | Available capacity | Details |
|---|---|---|---|---|---|
| 31/03/2012 20:17 | 01/04/2012 12:06 | CHEYLAS (LE) 2 | 259 MW | 0 MW | Details |
| 31/03/2012 15:15 | 01/04/2012 08:11 | GRAND-MAISON 9 | 152.5 MW | 0 MW | Details |
| 31/03/2012 15:14 | 01/04/2012 08:10 | GRAND-MAISON 2 | 152.5 MW | 0 MW | Details |
| 31/03/2012 10:11 | 01/04/2012 08:28 | SISTERON 1 | 124.2 MW | 0 MW | Details |
| 31/03/2012 10:11 | 01/04/2012 08:09 | CHEYLAS (LE) 1 | 259 MW | 0 MW | Details |
| 31/03/2012 06:43 | 31/03/2012 08:11 | SISTERON 1 | 124.2 MW | 0 MW | Details |
| 30/03/2012 14:51 | 31/03/2012 10:13 | PORCHEVILLE B 3 | 585 MW | 0 MW | Details |
| 30/03/2012 13:09 | 31/03/2012 07:56 | BORT 1 | 118.6 MW | 0 MW | Details |
| 28/03/2012 03:59 | 28/03/2012 08:17 | MONTEZIC 3 | 227.5 MW | 0 MW | Details |
| 28/03/2012 00:33 | 28/03/2012 08:16 | CHEYLAS (LE) 1 | 259 MW | 0 MW | Details |
| 27/03/2012 10:55 | 28/03/2012 08:16 | CHEYLAS (LE) 1 | 259 MW | 0 MW | Details |
| 27/03/2012 09:36 | 28/03/2012 08:14 | GRAND-MAISON 6 | 152.5 MW | 0 MW | Details |
| 26/03/2012 15:46 | 27/03/2012 07:33 | PORCHEVILLE B 3 | 585 MW | 0 MW | Details |
| 26/03/2012 14:18 | 27/03/2012 07:32 | PORCHEVILLE B 3 | 585 MW | 0 MW | Details |
| 26/03/2012 03:43 | 26/03/2012 05:21 | PROVENCE 5 | 595 MW | 0 MW | Details |
| 24/03/2012 01:52 | 25/03/2012 08:04 | CHEYLAS (LE) 1 | 259 MW | 0 MW | Details |
| 23/03/2012 17:14 | 24/03/2012 08:28 | BRENNILIS 3 | 134 MW | 0 MW | Details |
| 23/03/2012 05:46 | 23/03/2012 08:23 | CHEYLAS (LE) 1 | 259 MW | 0 MW | Details |
| 22/03/2012 17:39 | 23/03/2012 08:53 | PORCHEVILLE B 3 | 585 MW | 0 MW | Details |
| 21/03/2012 18:13 | 22/03/2012 08:01 | HAVRE (LE) 1 | 250 MW | 0 MW | Details |
| 21/03/2012 13:14 | 21/03/2012 13:14 | SPEM | 425 MW | 0 MW | Details |
| 21/03/2012 09:56 | 22/03/2012 07:58 | BELLEVILLE 2 | 1310 MW | 0 MW | Details |
| 21/03/2012 05:02 | 21/03/2012 06:49 | EMILE HUCHET 6 | 600 MW | 0 MW | Details |
| 20/03/2012 14:46 | 20/03/2012 14:46 | DK6 2 | 400 MW | 0 MW | Details |
| 20/03/2012 09:21 | 21/03/2012 07:39 | FESSENHEIM 2 | 880 MW | 0 MW | Details |
| 20/03/2012 07:06 | 21/03/2012 07:43 | BLENOD 5 | 440 MW | 0 MW | Details |
| 19/03/2012 11:29 | 20/03/2012 07:57 | HAVRE (LE) 4 | 580 MW | 0 MW | Details |
| 19/03/2012 04:33 | 19/03/2012 08:14 | COMBIGOLFE | 425 MW | 0 MW | Details |
| 19/03/2012 03:22 | 19/03/2012 07:48 | BLENOD 3 | 250 MW | 0 MW | Details |
| 18/03/2012 12:36 | 19/03/2012 07:43 | BRENNILIS 3 | 134 MW | 0 MW | Details |
| 18/03/2012 12:11 | 19/03/2012 08:42 | CHEYLAS (LE) 2 | 259 MW | 0 MW | Details |
| 16/03/2012 11:19 | 16/03/2012 14:12 | MONTEREAU 5 | 176 MW | 0 MW | Details |
| 16/03/2012 08:07 | 16/03/2012 11:37 | EMILE HUCHET 6 | 600 MW | 0 MW | Details |
| 16/03/2012 06:34 | 16/03/2012 06:34 | EMILE HUCHET 6 | 600 MW | 0 MW | Details |
| 15/03/2012 19:03 | 16/03/2012 09:48 | VITRY (-SUR-SEINE) 3 | 250 MW | 0 MW | Details |
| 15/03/2012 12:10 | 16/03/2012 08:43 | VILLARODIN 1 | 180 MW | 0 MW | Details |
| 15/03/2012 11:00 | 16/03/2012 07:39 | CORDEMAIS 5 | 580 MW | 0 MW | Details |
| 15/03/2012 08:36 | 16/03/2012 07:44 | PORCHEVILLE B 3 | 585 MW | 0 MW | Details |
| 14/03/2012 10:09 | 14/03/2012 13:56 | EMILE HUCHET 5 | 285 MW | 0 MW | Details |
| 14/03/2012 06:25 | 14/03/2012 07:51 | BOUCHAIN 1 | 250 MW | 0 MW | Details |
| 13/03/2012 07:15 | 13/03/2012 07:40 | REVIN 4 | 202 MW | 0 MW | Details |
| 13/03/2012 06:26 | 13/03/2012 09:11 | PONT SUR SAMBRE | 412 MW | 0 MW | Details |
| 12/03/2012 12:58 | 13/03/2012 23:12 | PROVENCE 4 | 230 MW | 0 MW | Details |
| 12/03/2012 09:30 | 13/03/2012 08:37 | HAVRE (LE) 1 | 250 MW | 0 MW | Details |
| 12/03/2012 07:48 | 12/03/2012 07:48 | EMILE HUCHET 6 | 600 MW | 0 MW | Details |
| 12/03/2012 06:46 | 12/03/2012 06:46 | EMILE HUCHET 4 | 115 MW | 0 MW | Details |
| 12/03/2012 05:12 | 12/03/2012 05:12 | PROVENCE 4 | 230 MW | 0 MW | Details |
| 12/03/2012 01:13 | 12/03/2012 03:30 | EMILE HUCHET 4 | 115 MW | 0 MW | Details |
| 11/03/2012 18:42 | 12/03/2012 08:16 | REVIN 4 | 202 MW | 0 MW | Details |
| 10/03/2012 09:45 | 11/03/2012 09:49 | CATTENOM 2 | 1300 MW | 0 MW | Details |
| 09/03/2012 22:46 | 10/03/2012 09:14 | REVIN 3 | 202 MW | 0 MW | Details |
| 09/03/2012 18:43 | 10/03/2012 09:14 | REVIN 4 | 202 MW | 0 MW | Details |
| 09/03/2012 17:34 | 10/03/2012 09:14 | CHEYLAS (LE) 1 | 259 MW | 0 MW | Details |
| 09/03/2012 10:12 | 10/03/2012 09:14 | GRAND-MAISON 11 | 157.1 MW | 0 MW | Details |
| 08/03/2012 17:29 | 09/03/2012 09:36 | PORCHEVILLE B 3 | 585 MW | 0 MW | Details |
| 08/03/2012 08:23 | 08/03/2012 08:54 | REVIN 2 | 202 MW | 0 MW | Details |
| 08/03/2012 04:53 | 08/03/2012 08:57 | CHEYLAS (LE) 2 | 259 MW | 0 MW | Details |
| 08/03/2012 03:46 | 08/03/2012 08:55 | CHEYLAS (LE) 1 | 259 MW | 0 MW | Details |
| 08/03/2012 03:18 | 08/03/2012 03:18 | PROVENCE 5 | 595 MW | 0 MW | Details |
| 07/03/2012 20:09 | 08/03/2012 08:51 | AIGLE (L ) 6 | 146 MW | 0 MW | Details |
| 07/03/2012 18:44 | 08/03/2012 08:53 | REVIN 4 | 202 MW | 0 MW | Details |
| 07/03/2012 18:04 | 08/03/2012 11:54 | PORCHEVILLE B 3 | 585 MW | 0 MW | Details |
| 07/03/2012 16:39 | 08/03/2012 08:52 | VILLARODIN 2 | 180 MW | 0 MW | Details |
| 07/03/2012 10:48 | 08/03/2012 11:53 | PORCHEVILLE B 1 | 585 MW | 0 MW | Details |
| 06/03/2012 23:04 | 07/03/2012 08:48 | CHEYLAS (LE) 1 | 259 MW | 0 MW | Details |
| 06/03/2012 19:24 | 07/03/2012 14:10 | FESSENHEIM 2 | 880 MW | 0 MW | Details |
| 06/03/2012 18:20 | 06/03/2012 18:59 | CHEYLAS (LE) 1 | 259 MW | 0 MW | Details |
| 06/03/2012 17:13 | 08/03/2012 08:50 | AIGLE (L ) 6 | 146 MW | 0 MW | Details |
| 06/03/2012 14:24 | 07/03/2012 14:11 | PORCHEVILLE B 3 | 585 MW | 0 MW | Details |
| 06/03/2012 08:46 | 07/03/2012 14:11 | PORCHEVILLE B 3 | 585 MW | 0 MW | Details |
| 05/03/2012 14:25 | 06/03/2012 09:14 | PORCHEVILLE B 1 | 585 MW | 0 MW | Details |
| 05/03/2012 14:12 | 06/03/2012 09:20 | PORCHEVILLE B 3 | 585 MW | 0 MW | Details |
| 05/03/2012 13:24 | 06/03/2012 09:14 | PORCHEVILLE B 1 | 585 MW | 0 MW | Details |
| 05/03/2012 08:40 | 06/03/2012 09:14 | PORCHEVILLE B 1 | 585 MW | 0 MW | Details |
| 05/03/2012 06:48 | 05/03/2012 09:28 | COMBIGOLFE | 425 MW | 0 MW | Details |
| 05/03/2012 02:00 | 06/03/2012 09:17 | HAVRE (LE) 4 | 580 MW | 0 MW | Details |
| 04/03/2012 21:51 | 05/03/2012 08:48 | REVIN 3 | 202 MW | 0 MW | Details |
| 04/03/2012 18:25 | 05/03/2012 09:08 | BELLEVILLE 2 | 1310 MW | 0 MW | Details |
| 03/03/2012 18:22 | 04/03/2012 08:47 | CHEYLAS (LE) 1 | 259 MW | 0 MW | Details |
| 03/03/2012 13:58 | 04/03/2012 10:05 | MAXE (LA) 2 | 250 MW | 0 MW | Details |
| 03/03/2012 00:17 | 03/03/2012 08:49 | CHEYLAS (LE) 1 | 259 MW | 0 MW | Details |
| 02/03/2012 20:05 | 03/03/2012 10:36 | MAXE (LA) 2 | 250 MW | 0 MW | Details |
| 02/03/2012 18:53 | 03/03/2012 08:49 | CHEYLAS (LE) 1 | 259 MW | 0 MW | Details |
| 01/03/2012 18:39 | 02/03/2012 08:47 | CHEYLAS (LE) 1 | 259 MW | 0 MW | Details |
| Years | Files |
|---|---|
| 2013 | File.zip |
| 2012 | File.zip |
| 2011 | File.zip |
| 2010 | File.zip |
Legal disclaimer
By accessing this website, each user accepts the present disclaimer.
All production data published on this website are for energy-market players only. Such players undertake to take appropriate steps to verify the quality of the published data. As a consequence, each user acknowledges that he/she uses such published data and information at its own risks.
The freely published production data are for information purposes only and are not legally binding. The producers participating to these publications and RTE make their best efforts to provide the information they have at their disposal on the publication dates, except in case of force majeure. In particular, the provisional information constitute the producers’ best estimate at the time of the publication and are not legally binding ; they may vary, notably on the basis of analysis that may be carried out on technical and surety aspects. The producers give no warranty whatsoever as to the updating of the estimates due to new information.
RTE and the electricity producers disclaim all liability in case of total or partial interruption of the publications and disclaim all liability for loss or damage which may result from the use by third parties of the data and/or information so published, including any mistakes, inaccuracies, or omissions in the data and/or information to the fullest extent permitted by law.
RTE and the producers shall not be liable for any damage resulting from the use of the data and/or information, except in case of wilful misconduct (« faute intentionnelle avérée ») and provided the user demonstrates a direct link between the wilful misconduct and the damage or the loss he/she suffers.